VIETNAM NATIONAL UNIVERSITY HO CHI MINH CITY HO CHI MINH CITY UNIVERSITY OF TECHNOLOGY TRAN HOANG ANH IMPROVING THE POOR MATERIAL MANAGEMENT IN CONSTRUCTION PROJECTS USING VALUE STREAM MAPPING Major: CONSTRUCTION MANAGEMENT Major Code: 8580302 MASTER’S THESIS HO CHI MINH CITY, July 2023 THIS THESIS IS COMPLETED AT HO CHI MINH CITY UNIVERSITY OF TECHNOLOGY – VNU-HCM Supervisor 1: Dr. Bui Phuong Trinh Supervisor 2: Assoc. Do Tien Sy Examiner 1: Assoc. Tran Duc Hoc Examiner 2: Dr.
Nguyen Hoai Nghia This master’s thesis is defended at HCM City University of Technology, VNU-HCM on July 10th, 2023. Master’s Thesis Committee: 1. Luong Duc Long - Chairman 2. Pham Vu Hong Son - Secretary 3.
Tran Duc Hoc - Reviewer 1 4. Nguyen Hoai Nghia - Reviewer 2 5. Pham Hai Chien - Member Approval of the Chairman of Master’s Thesis Committee and Dean of Faculty of Civil Engineering after the thesis being corrected (If any). CHAIRMAN OF THESIS COMMITTEE DEAN OF FACULTY OF CIVIL ENGIERING i VIETNAM NATIONAL UNIVERSITY-HO CHI MINH CITY SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY UNIVERSITY OF TECHNOLOGY Independence – Freedom – Happiness THE TASK SHEET OF MASTER’S THESIS Full name: Tran Hoang Anh Student code: 2170463 Date of birth: September 27th,1997 Place of birth: Ho Chi Minh City Major: Construction Management Major code: 858032 I.
THESIS TOPIC: Improving the poor material management in construction projects using Value Stream Mapping (Cải thiện việc quản lý vật liệu xây dựng trong các dự án bằng phương pháp Sơ đồ chuỗi giá trị) II. TASKS AND CONTENTS: - Evaluating the material management procedures in Vietnam construction firms. - Analyzing numerous significant aspects affecting poor material management in the case study project. - Proposing the coordination process, construction process of work in material management using value stream mapping (VSM) to minimize the causes of waste and bring efficiency to the business.
TASKS STARTING DATE: February, 2023 IV. TASKS ENDING DATE: June, 2023 V. Do Tien Sy and Dr. Bui Phuong Trinh Ho Chi Minh City, June 10th, 2023 SUPERVISORS HEAD OF DEPARTMENT DEAN OF FACULTY OF CIVIL ENGINEERING ii ACKNOWLEDGEMENT I would like to express my highly appreciation to all the people who directly and indirectly supported me during this study.
Without their direction, encouragement, and participation, this study would not have been possible. Firstly, I sincerely appreciate Assoc. Do Tien Sy and Dr. Bui Phuong Trinh.
They provided me with plenty of insightful comments, advice, and supervision, as well as supportive encouragement. Moreover, I would like to give a great altitude to Dr. Nguyen Thanh Viet, who had also supported and guided me to finish my thesis. Sincere thanks to my friends and the professionals in Vietnam's construction industry who patiently and sincerely offered me numerous suggestions and their opinions during the data collection and interviews.
Without their assistance, this master's thesis would not have come to an end. Last but not least, I want to express my sincere gratitude to my family for their support and love. Throughout the course of my master's thesis, they never stopped supporting and encouraging me and never gave up on me. iii ABSTRACT The improper management of materials during site activities is a crucial factor that has a negative impact on the performance of construction projects.
Materials management is problematic by shortages, supply delays, price fluctuations, damage, wastage, and a lack of storage space. Numerous studies were conducted to identify the issue causing poor material management, and solutions were offered. These solutions, however, only help to enhance a portion of the materials management. In the grand scheme of things, improper detail procedure control prevents proper material management in the construction project.
Therefore, Lean tool and Value Stream Mapping (VSM) were brought in this thesis to answer the question. The purpose of this thesis is to understand which activities are value-adding and non- value-adding to the current process and create a leaner and better material management. The objective is to identify and reduce "waste" in value streams in order to increase the efficiency of a specific value stream in material management. The study discovered the current construction material management procedure of construction projects/companies in Vietnam through interviews with experts in the field.
On the basis of the survey of the Case Study project, the thesis also discovered waste in the current process. The thesis developed the project's material management process, evaluated the process time, and identified the source of waste by applying Lean tools to the actual Case study process. The thesis used that information to identify the wasteful activities that needed to be stopped. The thesis also utilized Revit and Amis accounting software to improve process in the perspective of saving more time, requiring fewer staff members, and becoming more professional.
The results of the thesis showed that by using the VSM tool, in the same actual project, if comparing with using the traditional process, the new material management time from the process of calculating volume, ordering (including making contracts), examining and accepting input materials and warehousing is reduced 16.9% of the initial total time. More importantly, Value Added Time is now 50.6% of total time of the total material iv management process. This means that the company can reduce costs, waste, and effectively use the company's human resources. In other word, leaner processes will make it simpler to identify waste and quality problems, enhancing the productivity of material management in construction projects.
Moreover, the shortcomings of the previous material management procedure are studied, and the new procedure's application is verified. This helps investors or companies have an objective view and easily accept new effective proposals. As a result, production in general and material controlling in particular will be completed much faster and more efficiently, giving the company more flexibility to respond to shifting customer demands. In lean production, there is always a more effective way to complete every task because a business must keep up with the changing market in order to satisfy these new customer demands.
Key words: Construction Material Management, Lean tools, Lean in Construction, Value Stream Mapping (VSM), Improvement, Construction Projects, Vietnam. v TÓM TẮT LUẬN VĂN THẠC SĨ Việc quản lý vật liệu không hiệu quả trong các hoạt động tại công trường là một yếu tố quan trọng có tác động tiêu cực đến hiệu suất của các dự án xây dựng. Việc quản lý nguyên vật liệu gặp nhiều vấn đề do thiếu hụt, cung ứng chậm trễ, biến động giá cả, hư hỏng, lãng phí và thiếu kho bãi. Nhiều nghiên cứu đã được thực hiện để xác định vấn đề gây ra việc quản lý vật liệu kém và các giải pháp đã được đưa ra.
Tuy nhiên, những giải pháp này chỉ giúp cải thiện một phần công tác quản lý nguyên vật liệu. Nhìn chung, quy trình quản lý chi tiết không phù hợp sẽ ảnh hưởng tiêu cực đến việc quản lý vật liệu trong dự án xây dựng. Vì vậy, công cụ Tinh gọn và Sơ đồ dòng giá trị (VSM) được đưa vào luận văn này để trả lời câu hỏi trên. Mục đích của luận án này là để hiểu những hoạt động nào mang lại giá trị và không gia tăng giá trị cho quy trình hiện tại và tạo ra một hệ thống quản lý vật liệu tinh gọn và tốt hơn.
Mục tiêu là xác định và giảm "lãng phí" trong các dòng giá trị nhằm tăng hiệu quả trong quản lý vật chất. Nghiên cứu tìm ra quy trình quản lý vật liệu xây dựng hiện tại của các dự án/công ty xây dựng tại Việt Nam thông qua phỏng vấn các chuyên gia trong lĩnh vực này. Trên cơ sở khảo sát dự án, luận án cũng phát hiện ra sự lãng phí trong quy trình hiện tại. Luận án đã xây dựng quy trình quản lý nguyên vật liệu của dự án, đánh giá thời gian thực hiện các công tác, xác định nguồn gốc lãng phí bằng cách áp dụng các công cụ Lean vào quy trình của dự án thực tế.
Luận án đã sử dụng thông tin đó để xác định các hoạt động lãng phí cần phải chấm dứt. Luận án cũng sử dụng phần mềm kế toán Amis và phần mềm thiết kế Revit để cải tiến quy trình theo hướng tiết kiệm thời gian hơn, ít nhân viên hơn và chuyên nghiệp hơn. Kết quả của luận án cho thấy, với việc sử dụng công cụ VSM, trong cùng một công trình thực tế, nếu so sánh với việc sử dụng quy trình truyền thống thì thời gian quản lý vật tư mới từ khâu tính khối lượng, đặt hàng (kể cả làm hợp đồng), kiểm tra, nghiệm thu đầu vào nguyên vật liệu và nhập kho giảm được 16,9% so với tổng thời gian ban đầu. Quan trọng hơn, thời gian gia tăng giá trị hiện chiếm 50,6% tổng thời gian của toàn bộ quy trình quản lý vật liệu.
Điều này có nghĩa là công ty có thể giảm chi phí, lãng vi phí và sử dụng hiệu quả nguồn nhân lực của công ty. Hơn nữa, những thiếu sót của quy trình quản lý vật liệu trước đây được nghiên cứu và ứng dụng của quy trình mới được xác minh. Điều này giúp nhà đầu tư hoặc công ty có cái nhìn khách quan và dễ dàng chấp nhận những đề xuất mới hiệu quả. Do đó, hoạt động sản xuất nói chung và kiểm soát nguyên vật liệu nói riêng sẽ được hoàn thành nhanh hơn và hiệu quả hơn, giúp công ty linh hoạt hơn trong việc đáp ứng nhu cầu thay đổi của khách hàng.
Từ khóa: Quản lý vật liệu xây dựng, Công cụ tinh gọn, Tinh gọn trong xây dựng, Lập bản đồ dòng giá trị (VSM), Cải tiến, Dự án xây dựng, Việt Nam. vii AUTHOR’S COMMITMENT The undersigned below: Name: TRAN HOANG ANH Student ID: 2170463 Place and date of born: Ho Chi Minh City, September 27, 1997 Address: Ho Chi Minh City Declaring that the author completed the master's thesis with the title "IMPROVING THE POOR MATERIAL MANAGEMENT IN CONSTRUCTION PROJECTS USING VALUE STREAM MAPPING" under the guidance of the supervisors. All works, ideas, and materials that were obtained from other sources have been properly cited. Ho Chi Minh City, June 10th, 2023 Tran Hoang Anh viii Table of contents CHAPTER 1.
Objectives of the topic. Scope of study. Material management in Construction Projects. The process of construction materials management.
Construction Material Planning. Material Management Procedure. Construction Materials Handling. Stock and Loss/Waste Control.
Construction materials management issue. Effect of poor materials management. Effect of construction waste. Effect on quality of work.
Effect on profitability of the project. Current Materials Management Method. Value Stream Mapping (VSM). Waste in Value Stream definition.
Data collection techniques. Document analysis and observation. CASE STUDIES ON CURRENT INDUSTRY PRACTICE. Case study and limitation of research scope.
VSM application for the existing material management process of the project 55 4. VSM application for the future material management process of the project 66 CHAPTER 5. CONCLUSION AND RECOMMENDATION. Scientific and practical significances.
Recommendations and directions for research development. Directions for research development. 91 Material Calculation Using Revit. 92 x List of Figures Figure 1.
Components of material management [6]. General Procedure for Material Management of Large firms [6]. General Procedure for Material Management of Medium firms [6]. General Procedure for Material Management of Small firms [6].
Recommended Procedure for Material Management [6]. Preferred Materials Flow [13]. Proposed Road Map for the Implementation of Lean Manufacturing System. Examples of lean tools and principles in construction implementation and suggestions.
Value stream mapping icons. The process of the research .